MMERIDIANINFRASTRUCTURE
ProjectsTransportation & MobilityMumbai Coastal Road Tunnel
Transportation & Mobility · Completed

Mumbai Coastal Road Tunnel

Mumbai, Maharashtra · Municipal Corporation · 2024
₹3,950 CrContract value · 44 months
Mumbai Coastal Road Tunnel
Project overview

TBM · 12.2 m bore · Twin tube

Twin 2.07-kilometre road tunnels driven by a 12.2-metre tunnel-boring machine beneath a live metropolis and the sea — among the largest-diameter bores in the country.

Tunnel length2 × 2.07 km
Bore diameter12.2 m
Min. cover10 m below seabed
Contract value₹3,950 Cr
Duration44 months

Scope of work

  • Slurry TBM drive with segmental lining
  • Cross-passages and emergency egress
  • Saccardo tunnel ventilation system
  • Fire-life-safety, SCADA and lighting